14 Dec 2017

Leeds Bridge maintenance scheme starting in new year

Highways Transport

A programme of urgent maintenance works is to begin early in the new year on the historic Leeds Bridge.

From Monday 8 January 2018, work will start on essential works to strengthen, clean and repaint the bridge which carries traffic on Bridge End over the River Aire by The Calls in the city centre.

The project managed by Leeds City Council is expected to take 16 months to complete, with traffic restrictions being in place from late January meaning there no will be no access over the bridge for most northbound traffic (heading towards the city centre). Only the Elland Road Park and Ride service will continue to travel in that direction from 7am to 7pm on weekdays in order to minimise disruption for commuters.

A signed diversion will be established via Great Wilson Street, Crown Point Road, Kirkgate and The Calls for all other city-bound motorists. While the work is carried out, there will be no disruption to southbound traffic. Two-way access will continue to be provided for cyclists, and access will be maintained throughout for pedestrians.

The decision has been taken to carry out the work now in order to ensure some continuity and avoiding the bridge needing to be completely closed in the future.

Completed in 1873, the grade II-listed Leeds Bridge is made of wrought and cast iron, and the work to be carried out will see old concrete above the original ironwork deck removed and replaced with new stronger steel-reinforced concrete. Where needed, localised repairs will also be made to the ironwork before the bridge is then completely cleaned and repainted.

The bridge is also famous for being the location in 1888 of what is considered some of the world’s first-ever recorded moving film footage, when Louis Le Prince filmed traffic travelling across it.

Leeds City Council executive member for regeneration, transport and planning Councillor Richard Lewis said:

“Leeds Bridge is not only a historic asset for the city but also plays a key role for traffic coming in and out of the city centre. As with any such historic structure, it needs maintenance, repair and strengthening work from time to time to ensure it can continue to function well into the future. So it is essential this work now takes place with all efforts made to minimise the impact while it is carried out.”

Consultation has been carried out on the project with West Yorkshire Combined Authority and First Bus Leeds. Information will be given to all local residents and businesses, and advance signage will be shown around the bridge in the run-up to the work starting.

ENDS

For media enquiries please contact:

Roger Boyde,

Leeds City Council communications and marketing,

Tel: 0113 378 9164

Email: roger.boyde@leeds.gov.uk


For media enquiries contact:

Leeds City Council Communications team
communicationsteam@leeds.gov.uk